NATIONAL THERMAL POWER CORPORATION
LANDSLIDE
AT CHAMERA PROJECT
|
As the member of the International panel of independent consultants, ATES examined the problem of stability of slopes and abutments at Chamera Hydro Electric Project. A plan for monitoring slopes and intake structures has been
suggested.
|
 |
TALCHER
Seepage mitigation
The earthen dyke at Talcher
Thermal Power Station showed signs of distress due to heavy seepage through the
foundation. The problem was analyzed and remedial measures recommended. The implementation
of the recommendation is being carried out under the supervision of ATES.
|